Construction Updates

Rendering of Kruse addition

Project Details

Kruse is creating additional space to accommodate the full-day kindergarten program. 

Additions include:

  • Four kindergarten rooms with restrooms
  • A kitchen and cafeteria
  • Additional resource space
  • Dedicated art and music rooms
  • A new primary early learning playground
  • New student drop-off and parking areas

Kruse construction blueprints
Please click the image above for a larger version.

Project Timeline

Construction will begin in July 2018 and be completed in May 2019.

Updates

Please check back regularly for updates on the construction at Kruse.

October 15, 2018

The retention pond excavation has been completed. During the coming weeks, the storm and sanitary site work will begin. The installation of support steel is set to begin soon.

September 10, 2018

The addition was excavated and the concrete footings and foundation walls have been completed. The underground plumbing work is in progress and is scheduled to be finished this week.

August 20, 2018

Site excavation is in progress and excavation. Work is currently in progress to restore both locker rooms for use on August 23. 

August 6, 2018

Construction fencing has been installed and excavation work will begin soon. Work on the boiler piping, domestic water lines, electrical conduit, and sprinkler piping in the existing school building has been completed. Support steel in the locker rooms has been installed and parapet walls are set to begin.

July 16, 2018

Contractors have begun preparing for the demolition in both locker room areas. This work will include removing the suspended ceiling, sprinkler system piping, HVAC piping and electrical lighting system to accommodate the roof re-design. 